Spelga dam
Spelga Dam in the Mourne Mountains (South of Belfast) in Northern Ireland was under construction and started to move. All construction stopped for a year while it was fully investigated. The dam was needed to supply fresh wholesome water to the growing city of Belfast.
It turned out that the dam was being constructed on top of a “mother boulder” as described in the report conducted by the Structural Engineers at the time. All work was stopped and the boulder and clay underneath it was removed before the dam started again on top of the actual bedrock of the valley.
This was the last time explosives had been used in peacetime before the troubles and it led to the creation of the Structural Engineers Institute of Ireland.
[edit] Related articles on Designing Buildings
- Barrage.
- Caisson.
- Check dam.
- Coastal defences.
- Dam construction.
- Dredging.
- Dual purpose reservoirs.
- Flood defences.
- Hydropower.
- Irrigation.
- Land reclamation.
- Relief well.
- River engineering.
- Tidal lagoon power.
- Thames barrier.
- Trading systems for water resources.
- Water engineering.
- Water transfers and interconnections.
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Cut electricity bills to power growth
Coalition sends joint letter to the Chancellor.
Gasholders: a history in pictures. Book review.
Recognition, influence and growth
SocEnv identifies three strategic pillars in new strategy to 2045.
Discover the future of roofing, cladding and insulation.
New guidance for professional practice, cultural change and regulation in social housing.
The heritage of nuclear and conventional power stations.
New measures to stop people being ripped off
Government to protect families from cowboy builders and aggressive bailiffs.
New Futurebuild showcase brings an innovation-first approach.
National Planning Policy Framework
Understanding the 2026 changes.
ECA's public affairs priorities
Member consultation opens to shape priorities for 2027 to 2030.
Dutyholder responsibilities from 1 July 2026.
Where performance meets practice
The Building Envelope Stage at UKCW Birmingham.


















Comments
[edit] To make a comment about this article, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.